Progress Report on the Project to constrict two classrooms in Cameroon.
Betterways Africa received the grant of $8000 in December 2019 for the Construction of two classrooms for a village school attended by mostly orphaned and poor children in the North West Region of Cameroon.
Phase one of the project started in late January, after the end of year and new year festive period in 2020. Planning of the work with the host community was completed. The site was of the project was surveyed and approved for safety of the children.
The drawings of the foundation was prepared and a builder was identified, vetted and hired to begin building of the foundation in early March.
However due to the outbreak of the Corona virus the work could not commence due to a lockdown.
Material for construction wad however purchased in the nearby town of Bamenda and transported to the village.
The villagers conducted 5 days of community labour to prepare the site for construction of the two classrooms. This included clearing of bushes and transportation of sand and Stones purchased from a nearby location.
Construction of the foundation for building of the two classrooms started in May despite the continuing Corona virus, thanks to determination of the beneficiary community to pursue the work.
As of 15 June 2020, the construction of the foundation has been completed. This coincided with the onset of the heavy raining season.
Erection of the walls of the building will commence once the rains subside in late August 2020, and once the corona virus outbreak would have subsided as well by God’s grace. Thank you.
Betterways Africa received the grant of $8000 in December 2019 for the Construction of two classrooms for a village school attended by mostly orphaned and poor children in the North West Region of Cameroon.
Phase one of the project started in late January, after the end of year and new year festive period in 2020. Planning of the work with the host community was completed. The site was of the project was surveyed and approved for safety of the children.
The drawings of the foundation was prepared and a builder was identified, vetted and hired to begin building of the foundation in early March.
However due to the outbreak of the Corona virus the work could not commence due to a lockdown.
Material for construction wad however purchased in the nearby town of Bamenda and transported to the village.
The villagers conducted 5 days of community labour to prepare the site for construction of the two classrooms. This included clearing of bushes and transportation of sand and Stones purchased from a nearby location.
Construction of the foundation for building of the two classrooms started in May despite the continuing Corona virus, thanks to determination of the beneficiary community to pursue the work.
As of 15 June 2020, the construction of the foundation has been completed. This coincided with the onset of the heavy raining season.
Erection of the walls of the building will commence once the rains subside in late August 2020, and once the corona virus outbreak would have subsided as well by God’s grace. Thank you.
Betterway Africa International
The overall objective of this project is to renovate a 4-classrooms stone building of the primary school Bonayang village, which will offer the children a more conducive environment for learning, in a rural setting where there are limited services for education. It will offer education to the poor, disadvantaged village community with no alternative to advancement than through education. The transformative character of the project cannot be underestimated.
In partnership, Foundation for the Poor (FFP), Betterway Africa International (BAI) is committed to deliver vital assistance to the Bonayang community through the renovation of the dilapidated building of 4 classrooms stone building, as a contribution towards efforts for a solid a foundation for the education of its children. The renovated classrooms will provide a conducive environment for learning for about 100 children.
The full participation and ownership of the project by the beneficiary community, which will include the leveraging of locally available materials such as sand stones and lumber will be critical for the effective and timely completion of the project. Given resource constraints, utmost efficiency is essential for procurement and management of the project in order to reduce the risk of cost overruns.
This project is expected to be finished End-August! Thank you to all the DONORS - God bless their hearts!
In partnership, Foundation for the Poor (FFP), Betterway Africa International (BAI) is committed to deliver vital assistance to the Bonayang community through the renovation of the dilapidated building of 4 classrooms stone building, as a contribution towards efforts for a solid a foundation for the education of its children. The renovated classrooms will provide a conducive environment for learning for about 100 children.
The full participation and ownership of the project by the beneficiary community, which will include the leveraging of locally available materials such as sand stones and lumber will be critical for the effective and timely completion of the project. Given resource constraints, utmost efficiency is essential for procurement and management of the project in order to reduce the risk of cost overruns.
This project is expected to be finished End-August! Thank you to all the DONORS - God bless their hearts!
Current Project:
THE RENOVATION OF THE PRIMARY SCHOOL BONANYANG NGIE, NORTH WEST REGION OF CAMEROON
THE RENOVATION OF THE PRIMARY SCHOOL BONANYANG NGIE, NORTH WEST REGION OF CAMEROON
Village School Renovation Moves Forward with Support from U.S.-Based Foundation
Betterway Africa International, in partnership with Bonazah Community Organization, is making steady progress in renovating a historic four-classroom primary school in rural Cameroon. Thanks to a generous $3,360 grant from The Foundation for the Poor, Inc., based in the United States, the project has entered its third phase, with the goal of providing a safe and inspiring learning space for nearly 100 children.
A Four-Phase Restoration of a Historic School
The school building, a historic stone structure, had fallen into serious disrepair. The renovation is being carried out in four strategic phases:
- Phase 1: Demolition of the collapsing roof and construction of a new, durable roof.
- Phase 2: Repointing and plastering of the stone walls to improve structural integrity and preserve the building’s historic character.
- Phase 3 (Now underway): Construction of concrete floors and a surrounding veranda to improve hygiene, accessibility, and weather protection.
- Phase 4: Final touches, including painting, furnishing, and construction of modern toilets.
Community at the Heart of the Project
The success of this project relies on strong local partnerships:
“Bonazah Community Organization’s support has been invaluable,” said a project coordinator at Betterway Africa. “And the commitment of the local people—working side-by-side with us—is what gives this project lasting meaning.”
- Bonazah Community Organization, a grassroots nonprofit, is playing a critical role by facilitating project coordination, logistics, and community engagement.
- Local residents have joined hands to provide manual labor and ongoing support at the construction site—demonstrating a deep sense of ownership and commitment.
- Local authorities have also welcomed the initiative, recognizing its importance in improving educational outcomes and youth development in the area.
“Bonazah Community Organization’s support has been invaluable,” said a project coordinator at Betterway Africa. “And the commitment of the local people—working side-by-side with us—is what gives this project lasting meaning.”
More Than Bricks and Mortar
This is more than just a construction project—it is a symbol of hope, resilience, and investment in the next generation.
“This project is more than just a school renovation—it’s an investment in the future of our children,” said a local elder. “We are deeply grateful for this support.”
“This project is more than just a school renovation—it’s an investment in the future of our children,” said a local elder. “We are deeply grateful for this support.”
Gratitude to Our Supporters
Betterway Africa International extends its sincere thanks to The Foundation for the Poor, Inc. for their unwavering commitment to uplifting underserved communities. Their support is not just rebuilding a school—it’s restoring dignity, opportunity, and hope.
Donate to Support the Final Phase
Help us complete Phase 4: painting, furnishing, and toilet construction! Your gift—no matter the size—will directly help rural children learn in safety and dignity.
Donate Now: Secure online giving through our partner platform.
Get Involved
You can make a difference today
Donate Now: Secure online giving through our partner platform.
- $25: Classroom paint
- $50: One child’s desk and chair
- $100: Building materials for toilets
- $500: Sponsor a full classroom setup
Get Involved
You can make a difference today
- Spread the word: Share this story on social media
- Volunteer remotely: Help us fundraise or manage outreach
- Partner with us: We welcome organizations and donors to join our mission








